A Bird’s Eye view of Ongoing works

PROGRESS REPORT OF THE ONGOING WORKS OF MPHC AS ON 27th APRIL, 2016

Important Instructions

Sl. No.

Department

No. Of Works

E/COST (Rs in lac)

AMT. DEP.  (Rs in lac)

PROGRESS

REASON FOR
DELAY/REMARKS

ON SCHEDULE ON SCHEDULE
UPTO  6(SIX) MONTHS BEYOND 6(SIX) MONTHS
1 Police 110 7692.41 6620.33 81 9 20 Non availability of construction site,
disturbance by antisocial elements,
and poor response from the contractors.
2 Health 3 811.83 620.18 1 2 Delayed due to non-deposit
and non-sanctioning of the
requisite  funds.
3 NVS 8 573.83 393.50 1 7

Delayed due to late in
release of reimbursement bills.

4 Horticulture 1 400.00 349.68 1
5 AAI 1 244.01 146.40 1 Delayed due to changes
in the design of culverts,
communication gap between
the civil and electrical Engineers of AAI.
6 DIPR 1 215.00 175.50 1
7 YAS 1 48.05 42.03 1
125 9985.13 8347.62 86 10  29