Police Department Ongoing Project

Sl. No.

Source

Name

E/COST
(Rs in lac)

AMT. DEP.
(Rs in lac)

Date of Start

 

Prog. (%) Target Date
of Completion

REMARKS

1 MOPF
2011-2012 DHQ, TML Site handed over
by the Police Department
on 13th Nov. 2013.
Further the contractor
is not able to progress
fast due to some
practical problems.
MD spoke to SP Tamenglong
number of times and
the construction has
been speed up.
1. Dist. Police office
(ph-1)
179.32 156.84 14-11-13 75% 31.08.16
179.32 156.84
1 MOPF
2013-2014 Tamenglong District
Police line
i) Compound wall
fencing
70.00 61.19 10-09-14 10% 31-10-16 The contractor is not
able to progress fast due
to some practical
problems.
ii) 30 S.M. Barrack
with attached toilet
block-A
47.00 41.08 10-09-14 60% 31-07-16
iii) 30 S.M. Barrack
with attached toilet block-B
47.00 41.08 10-09-14 50% 31-07-16
164.00 143.35
1 MOPF
2013-2014 Imphal East, District
II) CMTW The progress of the
work has been discussed
with the contractor and
the same is likely to be
completed within the
target date of
completion.
i) Type-III Qtrs (G+3)
building-(Block-A)
195.00 170.46 15.04.15 65% 31.10.16
ii)Type-III Qtrs (G+3)
building -(Block-B)
195.00 170.46 13.02.15 80% 31.07.16
iii) DHQ, Porompat
i) Type-III Qtrs (G+3)
building
195.00 170.46 16.02.15 65% 31.10.16
IV) 2nd Bn. MR
i) Type-III Qtrs (G+3)
building
195.00 170.46 19.02.15 75% 31.07.16
V) 7th Bn. MR
i) Type-III Qtrs (G+3)
building
195.00 170.46 26.10.14 60% 31.10.16
975.00 852.30
1 MOPF
2014-2015 Imphal East,District
Basic Infrastructure
for 8th IRB unit (CDO
Bn)
i) 40 S.M. Barrack
with attached  Toilet
Block of 4 WC & 4
bath (Block-A)
105.00 95.80 20.02.15 60% 31.12.16 In progress.
ii) 40 S.M. Barrack
with attached  Toilet
Block of 4 WC & 4
bath (Block-B)
105.00 95.80 20.02.15 55% 31.12.16 In progress
iii) 40 S.M. Barrack
with attached  Toilet
Block of 4 WC & 4
bath (Block-C)
105.00 95.80 20.02.15 60% 31.12.16 In progress
iv) 40 S.M. Barrack
with attached  Toilet
Block of 4 WC & 4
bath (Block-D)
105.00 95.80 26.02.15 40% 31.12.16 In progress
v) Kitchen cum dining
hall
130.00 118.61 19.02.15 55% 31.12.16 In progress
550.00 501.81

1

MOPF

 

2014-2015 Imphal East, District
Basic Infrastructure
for 8th IRB unit (CDO Bn)

 

 

 

 

vi)Administrative
building

431.75

393.92

21.12.15

15%

30.04.17

In progress
vii) Approach road

117.95

107.62

20.12.15

 —

31.12.16

Yet to be started,
however the contractor
has been advised to
expedite early.
viii)Quarter guard

395.75

361.08

24.12.15

5%

31.12.16

In progress
ix)Barbedwire
fencing, with steel
gate-2nos.

7.13

6.50

22.12.15

15%

30.06.16

In progress
x) compound fencing
of Quarter guard with
steel gate

44.18

40.31

20.12.15

40%

31.12.16

In progress
xi) Sentry Tower-
4nos

53.24

50.48

20.12.15

10%

30.06.16

In progress

1050.00

959.91

1600.00

1461.72

2

 SCA

 

 2011-2012  (B) New projects
 

 

 

 

 1.Komlakhong P.O.P.
i) Sentry tower-Block
C & D

7.87

6.69

 —

 —

 —

For want of decision
from Police/Home
Department.

ii) G/ sump 15,000
ltrs cap. with O.H.
plateform.

6.08

5.17

 —

 —

 —

 

13.95

11.86

 

 

 

 

Note:- 10% State share is yet to be sanctioned by the Government.

2

SCA

2011-2012 (B)New projects
2.Hiyangthang POP  
i) 30 S.M barrack
2nos.

74.24

24.34

 —– 

 —– 

 ——

Site not yet
finalised/handed over
by the Police Deptt.
Estimates have  to be
recast because of time
overrun.
ii) kitchen dining hall

30.01

9.84

 —– 

 —– 

 ——

iii) T/B 6 bath

7.09

2.32

 —– 

 —– 

 ——

iv) T/B 6 W.C

8.16

2.68

 —– 

 —– 

 ——

v) G/ sump 15,000
ltrs cap. with O.H.
platform.

5.93

1.94

 —– 

 —– 

 ——

vi) Compound wall

33.11

10.85

  

  

 

vii) Sentry tower 3nos.

11.55

3.79

  

  

 

170.09

53.76

184.04

65.62

Note:- 10% State share is yet to be sanctioned by the Government.
3 A/Plan
2013-2014 P.S Buildings
Thoubal District
I) Arong
Nongmaikhong P.S
Changes in the
foundation design
involving additional
amount of Rs
2,75,200/-  was
cuncurred by the PHQ
on 21st Aug,
2015.Further necessary
action to expedite the
progress is on.
P.S bldg. (1st phase) 57.26 50.05 30.07.14 30% 30.08.16
CCP DISTRICT
I) Sangaikot P.S
 P.S bldg. (1st phase) 55.24 48.28 29.07.14 85% 31.05.16
112.50 98.33
3 A/Plan
2013-2014 CIAT SCHOOL, JIRIBAM
I) Class room 27.66 12.08 20.12.15 80% 30.6.16 In good progress
ii) Accommodation for
trainers-Block-A
17.70 7.74 20.12.15 80% 30.6.16 In good progress
iii) Accommodation
for trainers-Block-B
17.70 7.74 20.12.15 80% 30.6.16 In good progress
iv) Accommodation
for trainers-Block-C
17.70 7.74 20.12.15 80% 30.6.16 In good progress
v) Kitchen cum dining
hall  & store for
trainers
16.28 7.11 20.12.15 80% 30.6.16 In good progress
vi) Generator shed 1.02 0.45 20.12.15 80% 30.6.16 In good progress
98.06 42.86
210.56 141.19
3 A/Plan
2014-2015 Bishnupur District
Constn.& Repairing
work at Moirang P.S
i) Sentry Tower-2nos 10.33 9.03 23.12.15 35% 31.8.16 In progress.
ii) Repairing of old
existing  Barracks-
3nos
9.67 8.45 23.12.15 45% 30.6.16 In progress.
Imphal East District
i) Constn. Of JIC
office bldg. at CMTW
complex.
307.54 268.69 13.12.15 5% 30.06.17 In progress.
327.54 286.17
4 SRE
2014-2015 Tamenglong District
Awangkhul
i) 30 SM Barracks 10.33 9.03 23.12.15 35% 31.8.16 In progress.
ii) Toilet block-3wc & 3 bath 9.67 8.45 23.12.15 45% 31.8.16 In progress.
20.00 17.48
4 SRE
2015-2016 Tamenglong District
Basic Infrastructure &
Amenities for 143 BN.
CRPF  along NH-37
1) IRANG
a) CIVIL WORK
i) Renovation of OC’s
residence, Coy store &
Coy office.
5.12 4.48 02.04.16 5% 31.10.16 In progress.
b) ELECTRICAL
WORK
i)  Repairing  of IEI of
the  OC’s residence.
1.35 1.18  —  — 31.10.16 IEI will be started when
the civil works are
ready.
ii)  Repairing of IEI of
the  Coy office..
1.66 1.46  —  — 31.10.16
iii)  Repairing of IEI of
the  Coy store.
1.36 1.19  —  — 31.10.16
9.49 8.31
4 SRE
2015-2016 Tamenglong District
Basic Infrastructure &
Amenities for 143 BN.
CRPF  along NH-37
2) KHONGSANG
a) CIVIL WORK
i) Repairing  of
existing barracks-
2nos,SOS line.
24.02 21.00 24.04.16  — 31.10.16 Yet to be started
ii) Sentry Tower-3nos. 15.29 13.37 28.03.16 5% 31.10.16 In progress
b) ELECTRICAL
WORK
i)  Repairing of  IEI of
the barracks (Block-
A,B&C)
5.02 4.38  —  — 31.10.16  IEI will be started when
the civil works are
ready.
ii) Repairing of  IEI of
the officer mess
1.70 1.48  —  — 31.10.16
46.03 40.23
4 SRE
2015-2016 Tamenglong District
Basic Infrastructure &
Amenities for 143 BN.
CRPF  along NH-37
3) KHONGSANG
PORTAL-1
a) CIVIL WORK
i) Repairing of
existing barracks-
3nos.
15.38 13.45 27.03.16 5% 30.09.16 In progress
ii) Septic tank 30 user
Capacity.
1.21 1.06 27.03.16 5% 30.09.16 In progress
iii) Sentry Tower-
3nos.
17.88 15.64 24.04.16  — 30.09.16 Being started.
b) ELECTRICAL
WORK
i) Repairing of IEI of
the barracks (Block-
A&B)
3.35 2.93  —  — 30.09.16 IEI will be started when
the civil works are
ready.
ii) Repairing of IEI of
the barracks (Block-C)
1.68 1.47  —  — 30.09.16
39.50 34.55
4 SRE
2015-2016 Tamenglong District
Basic Infrastructure &
Amenities for 143 BN.
CRPF  along NH-37
4) AWANGKHUL
a) CIVIL WORK
i) Repairing of
existing barracks-
3nos.
15.38 13.45 02.04.16 5% 31.10.16 In progress.
b) ELECTRICAL
WORK
i) Repairing of IEI in
the barracks (Block-
A&B)
3.35 2.93  —  —  — IEI will be started when
the civil works are
ready.
ii) Repairing of IEI in
the barracks (Block-C)
1.68 1.47  —  —  —
115.44 100.94
5 SPA
2013-2014 TAMENGLONG DISTRICT
INFRASTRUCTURE
FOR NEW P. S AT
KHONGSANG
ALONG NH-37
i)  P.S. Building 182.31 143.51 21.01.15 80% 31.07.16 In progress.
ii)Type – III Qtr. 24.49 19.28 21.01.15 90% 31.05.16 In progress.
iii) J.C.O’s. Qtr./Transit camp 49.88 39.26 21.1.15 90% 31.05.16 In progress.
iv) Perimeter Fencing 64.88 51.07 21.01.15 90% 31.05.16 In progress.
v) Toilet block 6 W.C. 15.85 12.47 21.1.15 90% 31.05.16 In progress.
vi) Toilet block 6 Bath 11.26 8.87 21.1.15 90% 31.05.16 In progress.
vii) 20 kltrs. Capacity
ground sump with
overhead plateform
9.72 7.69 21.01.15 90% 31.05.16 In progress.
358.39 282.15
Note:- 10% State share is yet to be sanctioned by the Government.
5 SPA
2013-2014 CHANDEL DIST.
INFRASTRUCTURE
FOR MOREH P.S
CHECK POST AT
KONDONG
LAIREMBI AREA
i) 30 SM Barrack 43.36 34.11 12.08.14 100% Though structures were
completed and
scheduled for handing
over on 2nd sept, 2015 a
day before that there
was arson/fire by some
miscreants. A report
was sent to Police Deptt.
on 3rd sept, 2015 and
the estimates for
restoring the structures
have also been sent to
the Police Deptt. on 6th
Oct, 2015.
ii) Kitchen cum dining
hall
23.35 18.38 12.08.14 100%
iii) Compound wall
fencing.
44.30 34.85 12.08.14 100%
111.01 87.34
Note:- 10% State share is yet to be sanctioned by the Government.
6 13th FC 2012-13 Upgrdn of MPTS to
MPTC Pangei
i)  Water supply
scheme
374.80 327.80 09.03.14 80% 31.12.16 Progress held up due to non
finalisation/nonhanding
over of intake site by the
Police Department.
Addl. Infrastructure
for police training
centre at Jiribam
i)  Water supply
scheme
364.00 318.36 07.03.14 98% 31.05.16 Completed and being
commissioned.
738.80 646.16
6 13th FC 2012-13  POLICE STATIONS
IN RURAL &
REMOTE AREAS
A) TAMENGLONG P.
S.
i)  30 SM Barrack
(Block-B)
45.88 40.13 20.3.15 90% 31.05.16 Civil works completed
and IEI is in progress.
ii) Kitchen, store,
Dining hall
41.14 35.98 20.3.15 90% 31.05.16
iii) Sentry tower-2nos. 10.33 9.04 6.2.14 20% 31.08.16 Delayed due to
boundary problems
,which was settled on
4th April 2015. Further
the contractor is not
able to progress fast
due to some  practical
problems.
iv) Compound wall
fencing
47.80 41.80 6.2.14 25% 31.08.16
145.15 126.95
883.15 773.11
6 13th FC 2013-14 Upgrdn of MPTS to
MPTC Pangei
i) Type-III Qtr (G+2)
for Insp/Sub/Jem/SI
(Block-A)
163.92 143.37 26.11.15 40% 30.11.16 In progress
i) Type-III Qtr (G+2)
for Insp/Sub/Jem/SI
(Block-B)
163.92 143.37 30.11.15 40% 30.11.16 In progress
iii)Type-IV Qtr (G+1)
for GOs,Addl., A.C.,
Dy. S.P.)
161.25 141.03 09.12.15 20% 31.12.16 In progress
iv) kitchen-cum-
Dining Hall for Ors /
Rfm., Const.(200
capacity)
137.68 120.41 30.11.15 60% 30.11.16 In progress
v) 100 S.M.  2(Two)
storeyed Barrack, with
toilet facility
358.08 313.18 24.12.15 5% 31.12.16 In progress
vi) Accommodation
cum dining hall for officers trainees.
310.14 271.25 20.12.15 15% 31.12.16 In progress
vii) Indoor shooting
range with moving
target.
114.20 99.88 21.12.15 50% 31.12.16 In progress
viii) Kitchen cum
dining hall for JCO’s
(35 Capacity).
44.45 38.88 24.12.15 30% 31.12.16 In progress
ix) GO’s type-V qQtrs
for Jt. DIR. Dy. DIR
Asstt. DIR(G+1)
249.76 218.44 20.12.15 20% 31.12.16 In progress
1703.40 1489.81
6 13th FC 2013-14 ADDL.
INFRASTRUCTURE
FOR POLICE
TRAINING CENTER
AT JIRIBAM
i) Approach & internal
roads
173.92 152.12 20.12.15 90% 31.05.16 In progress
ii) Mini firing Range 51.99 45.47 24.12.15 10% 31.12.16 In progress
iii) Type-V Qtr. 55.50 48.54 24.12.15 10% 31.12.16 In progress
iv) Basic standard
obstacle coarse.
11.32 9.91 24.12.15 90% 31.05.16 In progress
v) Wireless office with
guard room (Double
storied).
103.84 90.81 24.12.15 10% 31.12.16 In progress
396.57 346.85
6 13th FC 2013-14 INFRASTRUCTURE
FOR POLICE
STATIONS IN
RURAL & REMOTE
AREAS
SENAPATI DISTRICT
 1. PURUL POLICE
STATION
i) Type-IV Qtr 37.45 32.75 22.12.15 7% 31.12.16 Land development in
progress.LOP approved
on 29th Jan,2016 only.
ii) Type-III Qtr 24.79 21.68 22.12.15 7% 31.12.16
iii) 50 SM Barrack 81.53 71.30 22.12.15 7% 31.12.16
iv) 30 SM Barrack 43.99 38.48 22.12.15 7% 31.12.16
v) Kitchen,
store,dinning hall
39.57 34.61 22.12.15 7% 31.12.16
vi) Sentry Tower
(Block-A)
5.21 4.55 22.12.15 7% 31.12.16
vii) Sentry Tower
(Block-B)
5.21 4.55 22.12.15 7% 31.12.16
viii) Sentry Tower
(Block-C)
5.21 4.55 22.12.15 7% 31.12.16
ix) Sentry Tower
(Block-D)
5.21 4.55 22.12.15 7% 31.12.16
x) Toilet block-6 bath 10.41 9.10 22.12.15 7% 31.12.16
xi) Toilet block-6 WC 13.10 11.45 22.12.15 7% 31.12.16
xii) Compound
fencing with steel
gate-1 no.
5.46 4.77 20.3.15 7% 31.10.15
xiii) 20Kltrs capacity
ground sump with
elevated platform
10.36 9.06 20.3.15 7% 31.10.15
287.50 251.40
6 13th FC 2013-14 INFRASTRUCTURE
FOR POLICE
STATIONS IN
RURAL & REMOTE
AREAS
SENAPATI DISTRICT
2. WILLONG POLICE
STATION.
i) Type-IV Qtr 39.16 34.24 22.12.15 8% 31.12.16 Land development in
progress.LOP approved
on 28th Jan,2016 only.
ii) Type-III Qtr 25.72 22.49 22.12.15 8% 31.12.16
iii) 50 SM Barrack 84.78 74.14 22.12.15 8% 31.12.16
iv) 30 SM Barrack 45.87 40.11 22.12.15 8% 31.12.16
v) Kitchen,
store,dinning hall
41.23 36.05 22.12.15 8% 31.12.16
vi) Sentry Tower
(Block-A)
5.37 4.70 22.12.15 8% 31.12.16
vii) Sentry Tower
(Block-B)
5.37 4.70 22.12.15 8% 31.12.16
viii) Sentry Tower
(Block-C)
5.37 4.70 22.12.15 8% 31.12.16
ix) Sentry Tower
(Block-D)
5.37 4.70 22.12.15 8% 31.12.16
x) Toilet block-6 bath 10.84 9.47 22.12.15 8% 31.12.16
xi) Toilet block-6 WC 13.28 11.61 22.12.15 8% 31.12.16
xii) Compound
fencing with steel
gate-1 no.
5.14 4.49 20.3.15 8% 31.10.15
287.50 251.40
2674.97 2339.46